Environmental risk assessment of Alborz Dam using Topsis and Fuzzy Topsis methods

Document Type : Research Article

Authors

1 Department of Civil Engineering, Faculty of Engineering, Qom University, Qom, Iran

2 Department of Civil Engineering, Faculty of Engineering, Islamic Azad University, Qaemshahr Branch, Iran

Abstract

The purpose of this study was to evaluate the environmental risks of Alborz Dam on Bababrood River in Babol city, using multi-criteria decision making methods. Initially, environmental identification of the study area was carried out, Then a list of environmental risks identified in the construction and exploitation phase was prepared and presented to environmental experts familiar with the Alborz dam area in the form of a questionnaire. environmental risks scored by environmental experts based on three indicators, Severity of occurrence, Probability of occurrence, Then environmental risks ranking was performed using TOPSIS and Fuzzy TOPSIS methods. The most important risks of Alborz dam using TOPSIS method in the construction phase, respectively: Was Obtained, Destruction of forest within the dam with a score of 0.926, Displacement of reservoir residents with a score of 0.837 And in the phase of operation: Thermal stratification of dam reservoir with a score of 0.847, Landslide with a score of 0.751. Also, the most important risks of the Alborz dam using the Fuzzy Topsis method in the construction phase, respectively: Was Obtained, Displacement of reservoir residents with a score of 0.682, Demolition of forest within the dam with a score of 0.677, And in the phase of operation, respectively: Thermal stratification of dam reservoir with a score of 0.645, Landslide with a score of 0.630. Finally, one method of integration (average rating method) was used to resolve the conflict between the results.

Keywords

Main Subjects


[1] R.V. Matalucci, Risk Assessment Methology for Dams (RAM-D SM), in:  Proceedings of 6rd International Conference on Probabilistic Safty Assessment and Management (PSAM 6), Puerto Rico, USA, (2002), pp.
.671-961
[2] J.R. Harrald, I. Renda-Tanali, G.L. Shaw, C.B. Rubin, S. Yeletaysi, Review of risk based prioritization/decision making methodologies for dams, US army corps for engineers, The George Washington University, Institute for Crisis, Disaster, and Risk Management, Washington, DC, 29,(2004)
[3] Z. Dongjian, G. Chongshi, L. Peng, Safety synthesis assessment of river-way levee, in:  73rd Annual Meeting of ICOLD, Tehran, Iran, May, (2005), pp. 1-6
[4] A. Rezaeifar, M.S. Jebel Ameli, A. Chaeibakhsh Langeroudi, Ranking of project risks using multi-criteria decision making models, in:  2nd International Project Management Conference, Ariana Research Group,
(1384).(in persian)
[5] F.J.C. Mendoza, A.G. Izquierdo, Design of a model to assess the environmental risk of leachate dams, Waste management, 28(11) (2008) 2122-2133.
[6] M. Karamouz, M. Dehghani, S.A. Asadollahi, A. Ahmadi, Assessment of Dams' Vulnerability with Strategic Management Approach: A Case Study, in:
Second national congress of dam construction, Islamic Azad University of Zanjan, (1388).(in persian)
[7] S.A.          Jozey,     S.M.       Monavari,             H.            Khosravani,
Environmental risk assessment of Lorestan Roudbar dam in construction phase by multi-indicator decision-making and model RAM-D, Environmental research, 3(6) (1392) 3-16.(in persian)
[8] S. Darvishi, S. Malmasi, A. Nazari Doost, Environmental risk assessment of Seydoun Dam in Khuzestan during construction using multi-criteria decision-making methods, in:  Third Conference on Environmental Planning and Management, University of Tehran, (1392).
(in persian)
[9] Qasempour Niari, E. Fataei, Environmental risk assessment of dams in building and exploitation phases using William Fine method (Case study: Emarat dam in Ardabil province), in:  First National Conference on Environmental Pollution with a Pure Land Focus, People's Society of Pure Life, (1393).(in persian)
[10] N.            Jafar       Zadeh    Haghighifard,       A.            Ashrafifar,            K.            Vershusaz,            Requirements and designing of environmental risk assessment of dam structures using TOPSIS method (Case study:  Ramhormoz dam), in:  International Conference on Science, Engineering and Environmental Technologies, Faculty of Environment of Tehran
University, (1394(.(in persian)
[11] S. Rezayan, S.A. Jozi, S. Ataee, Environmental risk assessment of Pavehroud Dam in construction phase using TOPSIS and RAM-D methods,(1395).(in persian)
[12] S. Malmasi, Z. Elahe Dad, Environmental risk assessment of dam construction projects using integrated multi-criteria decision making Case study: Azad Dam in Kurdistan province of Iran,(1396).(in persian)
[13] M.a.G.R.W.          Company,             Environmental     Impact
Assessment Studies of Alborz Dam, (1381).(in persian)
[14] M.J. Asgharpour, Multi-criteria decisions, Fifth Edition ed., University of Tehran, Tehran, Iran, (1387).(in persian)
[15] C.-L. Hwang, Kwangsun Yoonet al. Multiple attribute decision making: methods and applications: a state-of-the-art survey, Springer-Verlag New York, 24 (1981) 113.
[16] S.-J. Chen, C.-L. Hwang, Fuzzy multiple attribute decision making methods, in:  Fuzzy multiple attribute decision making, Springer, (1992), pp. 289-486.
[17] C.-T. Chen, Extensions of the TOPSIS for group decision-making under fuzzy environment, Fuzzy sets and systems, 114(1) (2000) 1-9.